Putney Bridge

Posted on 30/09/2014 by PSR Lighting Posted in Case Studies

As of 14 July 2014, Putney Bridge was closed for three months, except to pedestrians and dismounted cyclists, to undergo essential repairs by Wandsworth council to protect the bridge from damage caused by water penetration, which has contributed to the grade 2 listed structure’s poor road surface. While the bridge was closed for repair the original lighting columns and lanterns, which date back to 1886, have been refurbished by lighting specialist JW UK. The install was over seen by our very own Andy Jones.

SAMSUNG DIGITAL CAMERAThe lanterns themselves were originally gas fed and have had a number of updates including Sox, Son and cdott.

SAMSUNG DIGITAL CAMERAThe finished article looks amazing with the public regularly stopping to tell us so.

SAMSUNG DIGITAL CAMERANot often you will see Putney Bridge this quiet.

SAMSUNG DIGITAL CAMERAThe lanterns have now been converted to a Phillips fast flex LED system which will dramatically improve running costs.

 

 

 

 

 

 

A30 Launceston

Posted on 21/05/2014 by PSR Lighting Posted in Case Studies

AREA 1

Gary Taylor-Harris – PSR Lighting and Signs

TASK INSTRUCTION

Take down and relocate 2no advance directional signs. Install passive jerol posts in sockets installed by others. Remove old posts by cutting posts 150mm below ground level. Induction booked onsite for 0730.

 

photo

Old sign to be removed

RISK ASSESSMENTS REVIEWED

Removal of advance directional sign. Cut down/removal Of signage posts Install jerol posts Installation of advance directional sign

SKILLS REQUIRED

MEWP operative, 2no people working at height. Lorry mounted crane operative Signage installation

 

INDUCTION

Induction booked with Trevor Arnold of the Highways Agency at 730 pm As per Job notes. A mistake had been made on this part and the client wanted to induct 0730am and PSR was informed it would be 1930pm. As a change of plan Trevor inducted myself to then induct Steve and Rob because of Trevor’s prior engagements and I was local to Trevor. Therefore with the traffic management in place for the foreseeable future PSR was able to press forward with plans to start at 1930.

KEY ISSUES RAISED IN THE INDUCTION

Hospital locations Requirements on PPE Local recent issues An operative being crushed when a lorry was reversing, so always use a banksman -A near miss reported of a crane swinging his load over a live carriageway -All near misses or accidents need to be reported to Trevor Site rules Company polices Site specific details BT ducts run in between curb line and edge of concrete base for foundations at a depth of 600mm via trial holes. Agreed we would not put jack legs anywhere near this area. Trevor wanted to be advised when we was on and off site.

CARRYING OUT THE TASK INSTALLATION OF PASSIVE POSTS

photo 1

Pre cast base with pots installed

Steve and Rob carried out the installation of the jerol posts into the precast sockets. Importantly they made sure the posts were at the same height by marking the posts at the same point on each post and making sure they were level. This was important because the sign would need to be attached to the posts fully on both sides. Steve was controlling the lorry mounted crane and Rob was slinging and being Steve’s banksman whilst controlling the posts.

REMOVAL OF SIGNS

I took on the task of removing the existing signs. I could secure the sign on the MEWP whilst performing the controls on the tower. As the sign was coming down there was a few Clips that wouldnt come off and needed to be cut off. All nuts and bolts on the clips were removed due to questioned integrity of the thread.

REMOVAL OF OLD POSTS

This was carried out by the three of us. First we followed the job notes by digging down 150mm and cutting the posts down. We used a disc cutter for the cutting. As Steve started the cutter the start cord broke. The posts seemed to have a certain amount of movement so we agreed to try to break the concrete cap and lifting the posts out instead. This was carried out in a controlled manor.

photo 2

Old signs and posts removed

INSTALLATION OF SIGNS ONTO NEW POSTS

This take was carried out by all three of us. I was in the MEWP, Steve and Rob prepared the signs with bolts and securing braces for the bolts. We Installed the bottom panel of the ADS First. To get the mounting height of the sign we measured the signs total length Which was 3450mm. To add a gap between the signs this was increased to 3500mm. To hide the posts behind the sign we measured the top of the sign to the first rail, this was 60mm. I then subtracted half that value to move the sign up to cover the top of the posts. We then measured 3470mm from the top of the posts and this was the level of mounting height. This also married in with the given mounting height of 2000mm. The sign also had to Have a widthways clearance from the curb line of 1000mm. This worked out perfectly because then the sign was central with 800mm overhang of sign either side of the posts. With the first panel installed it was a case of placing the next 3no panels on top With clips holing the sign in place. With myself operating the MEWP Steve passed up the next 3no panels via A frame ladders. We made sure each panel lined up with each other via the text and diagrams on the Sign face. We then installed the second sign which was in one section. This was too heavy to carry by myself and in couldn’t be passed up due to the weight of it. We Decided Rob would help me.  To get the sign level one side was installed then a spirit level was used to make sure it was level. We then Put a covering of top soil of 100mm over the concrete base. Site was then Cleared of materials and tools and Trevor was contacted to let him know the job was completed.

photo 3

New posts and signs installed

JOB COMPLETED

Upon reflection the top sign should have been held in place via the lorry mounted crane. This has to go down as a near miss and will be looked at in the company’s method statements.

PSR Divisions

  • PSR Lighting

RSS Kent highways SE

  • M23 spur (Gatwick) westbound between M23 and J9A | Westbound | Congestion 22/08/2018
  • M23 spur (Gatwick) eastbound between J9A and M23 | Eastbound | Congestion 22/08/2018
  • M3 westbound between J3 and J4 | Westbound | Road Works 22/08/2018
  • A21 southbound between A228 and B2160 | Southbound | Congestion 22/08/2018
  • link road from M25 J7 anti-clockwise to M23 J8 southbound | Southbound | Congestion 22/08/2018
  • M25 J2 clockwise exit | Clockwise | Congestion 22/08/2018
  • M25 J9 clockwise exit | Clockwise | Congestion 22/08/2018
  • A27 westbound between A285 near Chichester (west) and B2144 | Westbound | Congestion 22/08/2018
  • A2 westbound between A2050 near Canterbury (west) and M2 | Westbound | Congestion 22/08/2018
  • M23 northbound between J9 and J8 | Northbound | Vehicle Fire 22/08/2018
  • Home
  • News
  • Case Studies
  • Contact us
  • Admin
PSR Lighting & Signs Ltd © 2015
  • Facebook
  • Google +
  • Twitter
This website uses cookies: By continuing to browse this site you accept this policy.Close
Privacy & Cookies Policy